1,180MW Bhikki plant opens: With accountability, good work must also be appreciated: CM

LAHORE: Chief Minister Shahbaz Sharif on Saturday inaugurated the fully Operational Combined Cycle of 1180MW gas-fired Bhikki Power Plant in Sheikhupura.

The plant’s CoD (Commercial Operation Date) was due in December, last year. But it missed the deadline three times or so due to different issues identified during various tests, including vibration issue, in one of the three turbines.

Published in Dawn, 20th May, 2018