Huaneng Shandong Ruyi (Pakistan) Energy (Pvt.) Limited

The application of Huaneng Shandong Ruyi (Pakistan) Energy (Pvt.) Limited for unconditional acceptance of upfront coal tariff for 2* 660 MW was approved on 31st March, 2017.

LocationQadarabad, District Sahiwal
Gross Capacity1320 MW
Net Capacity1214 MW
Primary FuelCoal
Backup Fuel-

Find Out More

Port Qasim Electric Power Company (Pvt.) Limited

The application of Port Qasim Electric Power Company (Pvt.) Limited for unconditional acceptance of upfront coal tariff for 2* 660 MW was approved on 13th February, 2017.

LocationPort Qasim, Karachi
Gross Capacity1320 MW
Net Capacity1214 MW
Primary FuelCoal
Backup Fuel-

Find Out More

Quaid-e-Azam Thermal Power (Pvt.) Limited

The tariff petition of Quaid-e-Azam Power (Pvt.) Limited for 1180.17 MW thermal power plant was approved on 14th April, 2016.

LocationBhikki, Sheikhupura
Gross Capacity1180.13 MW
Net Capacity1156.68 MW
Primary FuelRLNG
Backup FuelHSD

Find Out More

National Power Parks Management Company (Pvt.) Limited

The tariff petition of National Power Parks Management Company (Pvt.) Limited for 1223.106 MW thermal power plant was approved on 9th August, 2016.

LocationBalloki, Kasur
Gross Capacity1223.106 MW
Net Capacity1198.555 MW
Primary FuelRLNG
Backup FuelHSD

Find Out More

National Power Parks Management Company (Pvt.) Limited

The tariff petition of National Power Parks Management Company (Pvt.) Limited for 1230.540 MW thermal power plant was approved on 9th August, 2016.

LocationHaveli Bahadur Shah, Jhang
Gross Capacity1230.540 MW
Net Capacity1207.900 MW
Primary FuelRLNG
Backup FuelHSD

Find Out More